免费智能真题库 > 历年试卷 > 信息系统项目管理师 > 2018年下半年 信息系统项目管理师 上午试卷 综合知识
  第74题      
  章/节:   专业英语       

 
The (73) process differs from the (74) process in that the former is primarily concerned with acceptance of the deliverables, while the latter is primarily concerned with correctness of the deliverables.
 
 
  A.  Perform Quality Assurance
 
  B.  Validate Scope
 
  C.  Control Quality
 
  D.  Define Scope
 
 
 

 
  第73题    2008年上半年  
   60%
The project maintains a current and approved set of requirements over the life of the project by doin the following:
  第75题    2019年下半年  
   58%
Risk( )acknowledge the existence of a threat,but no proactive action is taken 。
  第74题    2021年上半年  
   67%
The key benefit of the Project( )is that it determines whether to scquire goods and services from outside the project,..
   题号导航      2018年下半年 信息系统项目管理师 上午试卷 综合知识   本试卷我的完整做题情况  
1 /
2 /
3 /
4 /
5 /
6 /
7 /
8 /
9 /
10 /
11 /
12 /
13 /
14 /
15 /
 
16 /
17 /
18 /
19 /
20 /
21 /
22 /
23 /
24 /
25 /
26 /
27 /
28 /
29 /
30 /
 
31 /
32 /
33 /
34 /
35 /
36 /
37 /
38 /
39 /
40 /
41 /
42 /
43 /
44 /
45 /
 
46 /
47 /
48 /
49 /
50 /
51 /
52 /
53 /
54 /
55 /
56 /
57 /
58 /
59 /
60 /
 
61 /
62 /
63 /
64 /
65 /
66 /
67 /
68 /
69 /
70 /
71 /
72 /
73 /
74 /
75 /
 
第74题    在手机中做本题