免费智能真题库 > 历年试卷 > 信息系统项目管理师 > 2015年下半年 信息系统项目管理师 上午试卷 综合知识
  第75题      
  章/节:   专业英语       

 
If the approved change requests have an effect on the project scope, then the corresponding component documents and cost baselines, and(75 )of the project management plan are revised and reissued to reflect the approved changes。
 
 
  A.  developing baselines
 
  B.  testing baselines
 
  C.  schedule baselines
 
  D.  ending baselines
 
 
 

 
  第74题    2021年上半年  
   67%
The key benefit of the Project( )is that it determines whether to scquire goods and services from outside the project,..
  第71题    2019年下半年  
   74%
( )seeks to perform root cause investigation as to what is leading identified trends.
  第73题    2010年下半年  
   54%
Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by (73).
   题号导航      2015年下半年 信息系统项目管理师 上午试卷 综合知识   本试卷我的完整做题情况  
1 /
2 /
3 /
4 /
5 /
6 /
7 /
8 /
9 /
10 /
11 /
12 /
13 /
14 /
15 /
 
16 /
17 /
18 /
19 /
20 /
21 /
22 /
23 /
24 /
25 /
26 /
27 /
28 /
29 /
30 /
 
31 /
32 /
33 /
34 /
35 /
36 /
37 /
38 /
39 /
40 /
41 /
42 /
43 /
44 /
45 /
 
46 /
47 /
48 /
49 /
50 /
51 /
52 /
53 /
54 /
55 /
56 /
57 /
58 /
59 /
60 /
 
61 /
62 /
63 /
64 /
65 /
66 /
67 /
68 /
69 /
70 /
71 /
72 /
73 /
74 /
75 /
 
第75题    在手机中做本题