A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should(75).
 
 
  A.  assign change tasks to project members
 
  B.  call a meeting of the configuration control board
 
  C.  change the scope baseline
 
  D.  postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline
 
 
 

 
  第72题    2012年下半年  
   72%
The Systems Development Life Cycle (SDLC) is a process of creating or altering information systems, and the models and m..
  第73题    2010年下半年  
   61%
Business intelligence (BI) is the integrated application of data warehouse, data miningand (73)
  第74题    2012年上半年  
   74%
(74) describees,indetail,the project's deliverables and the work required to create those deliverables.
   题号导航      2010年上半年 系统集成项目管理工程师 上午试卷 综合知识   本试卷我的完整做题情况  
1 /
2 /
3 /
4 /
5 /
6 /
7 /
8 /
9 /
10 /
11 /
12 /
13 /
14 /
15 /
 
16 /
17 /
18 /
19 /
20 /
21 /
22 /
23 /
24 /
25 /
26 /
27 /
28 /
29 /
30 /
 
31 /
32 /
33 /
34 /
35 /
36 /
37 /
38 /
39 /
40 /
41 /
42 /
43 /
44 /
45 /
 
46 /
47 /
48 /
49 /
50 /
51 /
52 /
53 /
54 /
55 /
56 /
57 /
58 /
59 /
60 /
 
61 /
62 /
63 /
64 /
65 /
66 /
67 /
68 /
69 /
70 /
71 /
72 /
73 /
74 /
75 /
 
第75题    在手机中做本题