2013年下半年 信息系统监理师 上午试卷 综合知识
第75题
关键词:
SOW
章/节:
专业英语
With a clear SOW a contractor completes work as specified, but the buyer is not pleased with the result. The contract is considered to be (75) .
A. incomplete because the buyer is not pleased
B. incomplete because the specs are incorrect
C. complete because the contractor meets the terms and conditions of the contract
D. complete because the contractor is satisfied
本题目为专供试卷题目。
【如需要,请开通】
您暂时无法使用本功能。
【如需要,请开通】
为保障您的权益,请登录
相关试题:专业英语
更多>
第72题
2017年上半年
55%
( )is used to model aggregates of information and the relationships these aggregates have to other.
第71题
2010年上半年
53%
The connection between two networks to form an internet is handled by a machine known as a (71)。
第72题
2014年上半年
67%
which type of the backup process backs up files that have been modified since the last time all data was backed up?( )
题号导航
2013年下半年 信息系统监理师 上午试卷 综合知识
本试卷我的完整做题情况
1
/
2
/
3
/
4
/
5
/
6
/
7
/
8
/
9
/
10
/
11
/
12
/
13
/
14
/
15
/
16
/
17
/
18
/
19
/
20
/
21
/
22
/
23
/
24
/
25
/
26
/
27
/
28
/
29
/
30
/
31
/
32
/
33
/
34
/
35
/
36
/
37
/
38
/
39
/
40
/
41
/
42
/
43
/
44
/
45
/
46
/
47
/
48
/
49
/
50
/
51
/
52
/
53
/
54
/
55
/
56
/
57
/
58
/
59
/
60
/
61
/
62
/
63
/
64
/
65
/
66
/
67
/
68
/
69
/
70
/
71
/
72
/
73
/
74
/
75
/
第75题 在手机中做本题