An example of scope verification is (73).
 
  A.  review the performance of an installed software module
 
  B.  managing changes to the project schedule
 
  C.  decomposing the WBS a work package level
 
  D.  performing a benefit/cost analysis to determine if we should proceed with the project




 
 