2012年上半年 上午试卷 综合知识
第 74 题
章/节 专业英语  
 
 
Your project is behind schedule due to conflict between team members .Haring resolved the conflict, to get the project back on schedule,you should consider (74).
 
  A.  crashing the Schedule
 
  B.  performing resource leveling
 
  C.  conducting reverse resource allocation Scheduling
 
  D.  utilizing the critical chair resources




 
 