2015年下半年 上午试卷 综合知识
第 73 题
章/节 专业英语  
 
 
(73)estimating is a technique for estimating the duration or cost of an activity or project using historical data from a similar activity or project.
 
  A.  Parametric
 
  B.  Analogous
 
  C.  Three-point
 
  D.  Expert judgment




 
 