2015年下半年 上午试卷 综合知识
第 74 题
章/节 专业英语  
 
 
Schedule compression shortens the project schedule without changing the project scope, to meet schedule constraints, imposed dates, or other schedule objectives. Schedule compression techniques include crashing and (74).
 
  A.  fast tracking
 
  B.  what-if scenario analysis
 
  C.  resource leveling
 
  D.  critical chain method




 
 