2008年下半年 上午试卷 综合知识
第 71 题
章/节 专业英语  
 
 
Define Activities is the process of identifying the specific actions to be performed to produce the (71).
 
  A.  project elements
 
  B.  work drafts
 
  C.  work package
 
  D.  project deliverables




 
 