全部科目 > 信息系统项目管理师 >
2008年下半年 上午试卷 综合知识
第 74 题
章/节 专业英语  
 
 
Estimating activity durations uses information on activity scope of (74), required resource types, estimated resource quantities, and resource calendars.
 
  A.  milestone
 
  B.  baseline
 
  C.  quality
 
  D.  work




 
 
相关试题     专业英语 

  第74题    2018年下半年  
The (73) process differs from the (74) process in that the former is primarily concerned with acceptance of the deliverables, while the latter is prim..

  第74题    2015年下半年  
Schedule compression shortens the project schedule without changing the project scope, to meet schedule constraints, imposed dates, or other schedule ..

  第74题    2013年下半年  
A(74)is a type of bar chart that illustrates a project schedule. It illustrates the start and finish dates of the terminal elements and summary elem..




更多复习资料
请登录电脑版软考在线 www.rkpass.cn

京B2-20210865 | 京ICP备2020040059号-5
京公网安备 11010502032051号 | 营业执照
 Copyright ©2000-2026 All Rights Reserved
软考在线版权所有