2018年上半年 上午试卷 综合知识
第 73 题
章/节 专业英语  
 
 
( )includes the processes required to ensure that the project includes all the work required , and only the work required , to compete the project successfully . managing the project scope is primarily concerned with defining and controlling what is not included in the project.
 
  A.  Create scope
 
  B.  Project stakeholder management
 
  C.  Preject scope management
 
  D.  Project cost management




 
 
相关试题     专业英语 

  第72题    2019年下半年  
( )provides guidance for the development and improvement of capabilities for introducing new and changed service into supported environment.

  第75题    2008年上半年  
Durin the project, requirements chan e for a variety of reasons. As needs chan e and as work proceeds, additional requirements are derived and chan es..

  第72题    2008年上半年  
The (71) is a eneral description of the architecture of a workflow mana ement system used by the WFMC, in which the main components and the associat..




更多复习资料
请登录电脑版软考在线 www.rkpass.cn

京B2-20210865 | 京ICP备2020040059号-5
京公网安备 11010502032051号 | 营业执照
 Copyright ©2000-2025 All Rights Reserved
软考在线版权所有