2018年上半年 上午试卷 综合知识
第 74 题
章/节 专业英语  
 
 
Estimate activity durations is the process of estimating the number of work periods needed to complete individual activities with estimated resources .The tools and techniques is not including().
 
  A.  expert judgment
 
  B.  analogous estimating
 
  C.  requirements traceability matrix
 
  D.  three-point estimating




 
 