( ) is a technique for estimating the duration or cost of an activity or a project using historical data from a similar activity or project.
 
  A.  Analogous estimating
 
  B.  Parametric estimating
 
  C.  Three-point estimating
 
  D.  Bottom-up estimating




 
 
相关试题     专业英语 

  第74题    2019年上半年  
Earned value management(EVM) integrates the scope baseline with the ( ) baseline, along with schedule baseline,to form the performance baseline, which..

  第75题    2010年下半年  
Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the (75) level.

  第73题    2017年下半年  
Validate Scope is the process of formalizing acceptance of the completed ( ).