全部科目 > 信息系统项目管理师 >
2010年上半年 上午试卷 综合知识
第 71 题
章/节 专业英语  
 
 
(71)assesses the priority of identified risks using their probability of occurring, the corresponding impact on project objectives if the risks do occur, as well as other factors such as the time frame and risk tolerance of the project constraints of cost, schedule, scope, and quality.
 
  A.  Quantitative Risk Analysis
 
  B.  Qualitative Risk Analysis
 
  C.  Enterprise Environmental Factors
 
  D.  Risk Management Plan




 
 
相关试题     专业英语 

  第75题    2011年上半年  
Precedence Diagramming Method(PDM) is a method used in activity sequencing.There are four types of dependencies or precedence relationships in PDM. Th..

  第72题    2016年下半年  
(72)is a term for data sets that are so large or complex that traditional data processing applications are inadequate. Challenges include analysis, ..

  第75题    2016年上半年  
The schedule management plan is a component of the project management plan. The schedule management plan may be formal or informal, highly detailed or..