2011年下半年 上午试卷 综合知识
第 74 题
章/节 专业英语  
 
 
There are strategies typically deal with threats or risk that may have negative impacts on project objectives if they occur, some other strategies are suggested to deal with risks with potentially positive impacts. (74) is a risk response strategy that may be adopted for either threats or opportunities.
 
  A.  share
 
  B.  Mitigate
 
  C.  Transfer
 
  D.  Acceptance




 
 
相关试题     专业英语 

  第72题    2018年上半年  
()is a decentralized, distributed and public digital ledger that is used to record transactions across many computers so that the record cannot be a..

  第73题    2015年下半年  
(73)estimating is a technique for estimating the duration or cost of an activity or project using historical data from a similar activity or project..

  第73题    2008年上半年  
The project maintains a current and approved set of requirements over the life of the project by doin the following:
· (73)all changes ..




更多复习资料
请登录电脑版软考在线 www.rkpass.cn

京B2-20210865 | 京ICP备2020040059号-5
京公网安备 11010502032051号 | 营业执照
 Copyright ©2000-2025 All Rights Reserved
软考在线版权所有