第 74 题
章/节 专业英语  
 
 
In project management , a (73 ) is a listing of a project’s milestones, activities, and deliverables, usually with intended start and finish dates. Those items are often estimated in terms of resource ( 74) ,budget and duration, linked by dependencies and scheduled events.
 
  A.  finding
 
  B.  balance
 
  C.  allocation
 
  D.  distribution




 
 