全部科目 > 系统集成项目管理工程师 >
2015年下半年 上午试卷 综合知识
第 73 题
章/节 专业英语  
 
 
The Project Management Triangle is a model of the constraints of project management.These constraints have been listed as scope(or quality),(73),and cost.
 
  A.  resource
 
  B.  time
 
  C.  plan
 
  D.  tool




 
 
相关试题     专业英语 

  第71题    2022年上半年  
A grid for mpping the probability of occurrence of each impact on project objectives if that risk occurs is used in ().

  第74题    2015年上半年  
(74) is the output of the quality planning.

  第72题    2022年上半年  
Machine learning a fundamental concept of () research since the field ′s inception,is the study of computer algorithms that improve automatically ..