Which of the following statement related to PMO is not correct? (71)
 
  A.  The specific form, function, and structure of a PMO are dependentupon the needs of the organization that it supports.
 
  B.  One of the key features of a PMO is managing shared resources across all projects administered by the PMO.
 
  C.  The PMO focuses on the specified project objectives.
 
  D.  The PMO optimizes the use of shared organizational resources across all  projects.




 
 
相关试题     专业英语 

  第71题    2016年下半年  
(71)is a paradigm for enabling network access to a scalable and elastic pool of shareable physical or virtual resources with self-service provisioni..

  第73题    2026年上半年  
In project time management, activity definition is the process of identifying and documenting the specific action to be performed to produce the proje..

  第74题    2015年上半年  
(74) is the output of the quality planning.




更多复习资料
请登录电脑版软考在线 www.rkpass.cn

京B2-20210865 | 京ICP备2020040059号-5
京公网安备 11010502032051号 | 营业执照
 Copyright ©2000-2026 All Rights Reserved
软考在线版权所有