全部科目 > 系统集成项目管理工程师 >
2017年下半年 上午试卷 综合知识
第 75 题
章/节 专业英语  
 
 
( )is the approved version of the time-phased project budget excluding any management reserves which can only be changed through formal change control precedures and is used as a basis for comparison to actual results。
 
  A.  The control accounts
 
  B.  Funding requirement
 
  C.  The cost estimates
 
  D.  The cost baseline




 
 