第 75 题
章/节 专业英语  
 
 
The Development of Project Management Plan Process includes the actions necessary to define, prepare, integrate, and coordinate all constituent plans into a (75)
 
  A.  Project Scope Statement
 
  B.  Project Management Plan Project
 
  C.  Forecasts
 
  D.  Charte




 
 