第 72 题
章/节 专业英语  
 
 
Categories of risk response are (72).
 
  A.  Identification, quantification, response development, and response control.
 
  B.  Marketing, technical, financial, and human
 
  C.  Avoidance, retention, control, and deflection
 
  D.  Avoidance, mitigation, acceptance, and Transferring




 
 