全部科目 > 系统集成项目管理工程师 >
2010年上半年 上午试卷 综合知识
第 75 题
章/节 专业英语  
 
 
A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should(75).
 
  A.  assign change tasks to project members
 
  B.  call a meeting of the configuration control board
 
  C.  change the scope baseline
 
  D.  postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline




 
 
相关试题     专业英语 

  第72题    2016年下半年  
Unlike more traditional embedded systems a full-fledged CPS is typically designed as a(72)of interacting elements with physical input and output ins..

  第73题    2011年上半年  
(73) are the four major activities of software configuration management.
① configuration identification ② statement report ③ change control<..

  第73题    2009年下半年  
(73) is a method used in Critical Path Methodology for constructing a project schedule network diagram that uses boxes or rectangles, referred to as n..