第 75 题
章/节 专业英语  
 
 
A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should(75).
 
  A.  assign change tasks to project members
 
  B.  call a meeting of the configuration control board
 
  C.  change the scope baseline
 
  D.  postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline




 
 
相关试题     专业英语 

  第74题    2018年下半年  
Quality management ensures that an organization product or service is consistent. It has four main components: quality planning, quality assurance, ( ..

  第71题    2013年上半年  
Modem computers based on (71) are millions to billions of times more capable than the early computers, which occupy a fraction of the space. Simple co..

  第73题    2012年下半年  
Managing risk and documenting them is veryimportant inproject planning process. You are in the process of defining keyrisks, including constraints and..




更多复习资料
请登录电脑版软考在线 www.rkpass.cn

京B2-20210865 | 京ICP备2020040059号-5
京公网安备 11010502032051号 | 营业执照
 Copyright ©2000-2026 All Rights Reserved
软考在线版权所有