In a project plan, when the project manager schedules activities, he (or she) often uses ( ) method,This method, precedence relationships between activities are represented by circles connected by one or more arrows. The length of the arrow represents the duration of the relevant activity.
 
  A.  causality diagram
 
  B.  Gantt chart
 
  C.  histogram
 
  D.  arrow diagram




 
 