2012年下半年 上午试卷 综合知识
第 75 题
章/节 专业英语  
 
 
Several riskresponse strategies are available. (75) the risk simply gives another party responsibility for itsmanagement,it does not eliminate risk.
 
  A.  Avoiding
 
  B.  Mitigating
 
  C.  Accepting
 
  D.  Transferring




 
 