全部科目 > 系统集成项目管理工程师 >
2012年下半年 上午试卷 综合知识
第 75 题
章/节 专业英语  
 
 
Several riskresponse strategies are available. (75) the risk simply gives another party responsibility for itsmanagement,it does not eliminate risk.
 
  A.  Avoiding
 
  B.  Mitigating
 
  C.  Accepting
 
  D.  Transferring




 
 
相关试题     专业英语 

  第72题    2019年上半年  
( ) is the extension of internet connectivity into physical devices and everyday objects. Embedded with electronics, internet connectivity, and othe..

  第72题    2020年下半年  
( )is called the gateway of network security, which is used toidentify what kind of data packets can enter the enterprise intranet。

  第74题    2014年上半年  
In project management , a (73 ) is a listing of a project’s milestones, activities, and deliverables, usually with intended start and finish dat..