全部科目 > 系统集成项目管理工程师 >
2013年下半年 上午试卷 综合知识
第 75 题
章/节 专业英语  
 
 
In project management, a (75) is a list of a project's milestones, activities, and deliverables, usually with intended start and finish dates. Those items are often estimated in terms of resource allocation, budget and duration, linked by dependencies and scheduled events.
 
  A.  schedule
 
  B.  WBS
 
  C.  SOW
 
  D.  charter




 
 
相关试题     专业英语 

  第72题    2020年下半年  
( )is called the gateway of network security, which is used toidentify what kind of data packets can enter the enterprise intranet。

  第75题    2022年下半年  
()is not the communication technical that may be used for the virtual team.

  第72题    2026年上半年  
(72)is not included in the main contents of the operation and maintenance of the information system.