第 75 题
章/节 专业英语  
 
 
()is the process of monitoring the status of the project to update the projects costs and managing changes to the cost baseline.
 
  A.  Control costs
 
  B.  Costs udates
 
  C.  Validate scope
 
  D.  Monitor communications




 
 