uring the systems planning phase, a systems analyst conducts a (71)activity to study the systems request and recommend specific action. After obtaining an authorization to proceed, the analyst interacts with (72) to gather facts about the problem or opportunity, project scope and constraints, project benefits, and estimated development time and costs. In many cases, the systems request does not reveal the underlying problem, but only a symptom. A popular technique for investigating causes and effects is called (73)The analyst has analyzed the problem or opportunity, defined the project scope and constraints, and performed (74)to evaluate project usability, costs, benefits, and time constraints. The end product of the activity is (75). The main content must include an estimate of time, staffing requirements, costs, benefits, and expected results for the next phase of the SDLC.
 
  A.  system proposal
 
  B.  feasibility analysis
 
  C.  fact-finding
 
  D.  requirement analysis




 
 
相关试题     专业英语 

  第73题    2013年上半年  
Feasibility should be measured throughout the life cycle of system development. The scope and complexity of an apparently feasible project can change ..

  第72题    2024年上半年  
uring the systems planning phase, a systems analyst conducts a (71)activity to study the systems request and recommend specific action. After obtain..

  第71题    2025年下半年  
The analysis phase answers the questions of who will use the system, what the system will do, and where and when it will be used. During this phase, t..