A formally chartered group responsible for reviewing,evaluating,
approving,delayingor rejecting changes to the project,and for recording and communication such decisions. It is the ().
 
  A.  Change Control System
 
  B.  Change Control Board
 
  C.  Change Control Tool
 
  D.  Change Management Plan




 
 
相关试题     专业英语 

  第72题    2014年上半年  
which type of the backup process backs up files that have been modified since the last time all data was backed up?( )

  第75题    2009年上半年  
Configuration management is the process of managing change in hardware, software, firmware, documentation, measurements, etc. As change requires an in..

  第71题    2017年下半年  
( )concerns a cycle of organizational activity : the acquisition of information from one or more sources , the custodianship and the distribution of..