Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other. (74) is following the process- Estimate Activity Durations.
 
  A.  Develop Schedule
 
  B.  Estimate Activity Resources
 
  C.  Define Activities
 
  D.  Sequence Activities




 
 