全部科目 > 信息系统监理师 >
2010年下半年 上午试卷 综合知识
第 75 题
章/节 专业英语  
 
 
Which of the following is not part of the change-management process of IT supervisor? (75).
 
  A.  change analyses
 
  B.  change evaluation
 
  C.  change acquisition
 
  D.  change executing




 
 
相关试题     专业英语 

  第72题    2017年上半年  
( )is used to model aggregates of information and the relationships these aggregates have to other.

  第71题    2012年上半年  
Which is the second layer from the bottom in Open System Interconnection Reference Model? (71).

  第75题    2023年上半年  
With a clear SOW a contractor completes work as specified, but the buyer is not pleased with the result. The contract is considered to be (75) .