You are a project manager for a small project. Your project was budgeted for ¥500,000 over a six-week period. As of today, you’ve spent Y260,000 of your budget to complete work that you originally expected to cost ¥280,000. According to your schedule, you should have spent Y300,000 by this point. Based on these circumstances, your project could be best described as (74).
 
  A.  ahead of schedule
 
  B.  behind schedule
 
  C.  on schedule
 
  D.  having not enough information provided




 
 
相关试题     专业英语 

  第75题    2023年下半年  
The difference value between Budgeted Cost for work Performed and Actual Cost for Work Performed is( ).

  第73题    2019年上半年  
The perform Integrated Change Contorl process is the ultimate responsibility of the (73).Although changes may be initiated verbally,they should be r..

  第75题    2016年上半年  
When a process is in control, what do you want to do with the process?(75).




更多复习资料
请登录电脑版软考在线 www.rkpass.cn

京B2-20210865 | 京ICP备2020040059号-5
京公网安备 11010502032051号 | 营业执照
 Copyright ©2000-2025 All Rights Reserved
软考在线版权所有