2012年上半年 上午试卷 综合知识
第 73 题
章/节 专业英语  
 
 
Which of the following is not an input to quality planning? (73).
 
  A.  cope statement
 
  B.  regulations
 
  C.  work results
 
  D.  standards




 
 
相关试题     专业英语 

  第75题    2013年上半年  
Workarounds are determined during which risk management process? (75)

  第75题    2014年上半年  
Which of the following  represents the estimated value of the work actually accomplished?()

  第75题    2013年下半年  
With a clear SOW a contractor completes work as specified, but the buyer is not pleased with the result. The contract is considered to be (75) .