With a clear SOW a contractor completes work as specified, but the buyer is not pleased with the result. The contract is considered to be (75) .
 
  A.  incomplete because the buyer is not pleased
 
  B.  incomplete because the specs are incorrect
 
  C.  complete because the contractor meets the terms and conditions of the contract
 
  D.  complete because the contractor is satisfied




 
 