2015年上半年 上午试卷 综合知识
第 73 题
关键词 WBS  
章/节 专业英语  
 
 
(73)is the budgeted amount for the work actually completed on the schedule acticity or WBS comonent during a given period。
 
  A.  Planned value
 
  B.  Actual cost
 
  C.  Earned value
 
  D.  Cost variance




 
 