全部科目 > 信息系统监理师 >
2015年上半年 上午试卷 综合知识
第 74 题
关键词 CPI  
章/节 专业英语  
 
 
What does a CPI of 80% mean? (74).
 
  A.  As of now we expect the total pr gject cost of 80% more than planned
 
  B.  When the project is completed, we will have spent 80% more
 
  C.  Your project is only progressing at 80% of that planned
 
  D.  Your project is only getting 80 cents out of every RMB invested




 
 
相关试题     专业英语 

  第75题    2010年上半年  
(75) is not the tool name for quality controlling used in the figure below.

  第75题    2018年下半年  
The top management of a company will review the organization’s management system, the management review will include consideration of :
( a..

  第74题    2014年下半年  
In all projects,needs must be tempered by schedule ,cost and resource constraints. Project success depends primarily on (74).