What does a CPI of 80% mean? (74).
 
  A.  As of now we expect the total pr gject cost of 80% more than planned
 
  B.  When the project is completed, we will have spent 80% more
 
  C.  Your project is only progressing at 80% of that planned
 
  D.  Your project is only getting 80 cents out of every RMB invested




 
 