2016年下半年 上午试卷 综合知识
第 75 题
章/节 专业英语  
 
 
In project time management processes,(75)involves identifying and documenting the relationships between project activities.
 
  A.  activity definition
 
  B.  activity sequencing
 
  C.  schedule control
 
  D.  schedule development




 
 