2017年下半年 上午试卷 综合知识
第 74 题
章/节 专业英语  
 
 
Change control within information technology ( IT ) systems is a formal process used to ensure that changes to product or system are introduced in a controlled and coordinated manner . It( )the possibility that unnecessary changes will be introduced to a system without forethought.
 
  A.  adds
 
  B.  removes
 
  C.  produces
 
  D.  reduces




 
 
相关试题     专业英语 

  第75题    2013年上半年  
Workarounds are determined during which risk management process? (75)

  第71题    2013年下半年  
Since risk is associated with most projects, the best course of action is to (71)

  第73题    2018年下半年  
The organization shall undertake change in a planned and systematic manner, taking account of the review of the potential consequences of changes and ..