The perform Integrated Change Contorl process is the ultimate responsibility of the (73).Although changes may be initiated verbally,they should be recorded in writtern form and entered into the(74)system.
 
  A.  resource manager
 
  B.  division manager
 
  C.  functional manager
 
  D.  project manager




 
 