The perform Integrated Change Contorl process is the ultimate responsibility of the (73).Although changes may be initiated verbally,they should be recorded in writtern form and entered into the(74)system.
 
  A.  resource manager
 
  B.  division manager
 
  C.  functional manager
 
  D.  project manager




 
 
相关试题     专业英语 

  第74题    2010年上半年  
Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other. (74) is ..

  第74题    2022年下半年  
Maintenance activities do not include (74).

  第74题    2018年上半年  
Every documented change request needs to be either approved or rejected by a responsible individual sually( ).