When required,the Perform Integrated Change Control process includes a ( ),Which is a formally chartered group responsible for reviewing,evaluating,approving, deferring, or rejecting changes to the project and for recording and communicating such decisions.
 
  A.  BBC
 
  B.  CCB
 
  C.  BCB
 
  D.  CBC




 
 
相关试题     专业英语 

  第73题    2021年上半年  
A formally chartered group responsible for reviewing,evaluating,
approving,delayingor rejecting changes to the project,and for recording and co..

  第74题    2023年上半年  
Schedule control is concerned with all the followings except (74) .

  第75题    2015年下半年  
A software requirements specification is that ( ).