When required,the Perform Integrated Change Control process includes a ( ),Which is a formally chartered group responsible for reviewing,evaluating,approving, deferring, or rejecting changes to the project and for recording and communicating such decisions.
 
  A.  BBC
 
  B.  CCB
 
  C.  BCB
 
  D.  CBC




 
 