2023年上半年 上午试卷 综合知识
第 75 题
关键词 SOW  
章/节 专业英语  
 
 
With a clear SOW a contractor completes work as specified, but the buyer is not pleased with the result. The contract is considered to be (75) .
 
  A.  complete because the contractor meets the terms and conditions of the contract
 
  B.  incomplete because the buyer is not pleased
 
  C.  complete because the contractor is satisfied
 
  D.  incomplete because the specs are incorrect




 
 