With a clear SOW a contractor completes work as specified, but the buyer is not pleased with the result. The contract is considered to be (75) .
 
  A.  complete because the contractor meets the terms and conditions of the contract
 
  B.  incomplete because the buyer is not pleased
 
  C.  complete because the contractor is satisfied
 
  D.  incomplete because the specs are incorrect




 
 
相关试题     专业英语 

  第71题    2021年上半年  
()describes how the information about the items of the project will be recorced and updated so that the product,service,or result ofthe proiect remain..

  第71题    2018年上半年  
The information is circulated through communication processes.( )is not included in Work Performance Information.

  第75题    2012年上半年  
To determine whether or not the employee correctly understands the message, the project manager needs to (75).




更多复习资料
请登录电脑版软考在线 www.rkpass.cn

京B2-20210865 | 京ICP备2020040059号-5
京公网安备 11010502032051号 | 营业执照
 Copyright ©2000-2025 All Rights Reserved
软考在线版权所有