免费智能真题库 > 历年试卷 > 信息系统项目管理师 > 2008年下半年 信息系统项目管理师 上午试卷 综合知识
第75题      2008年下半年 信息系统项目管理师 上午试卷 综合知识
所属知识点   专业英语       
考点辞典   ping

 
Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to (75) progress.
 
 
  A.  analyze
 
  B.   track
 
  C.  level
 
  D.  extend
 
 
 

  专业英语 知识点 更多相关真题:    更多>  
 
  第74题    2010年下半年  
   63%
Configuration management system can be used in defining approval levels for authorizing changes and providing a method to validate approved changes.(74) is not a project configura..
  第72题    2009年下半年  
   59%
The strategies for handling risk comprise of two main types:negative risks, and positive risks. The goal of the plan is to minimize threats and maximize opportunities.When deali..
  第75题    2016年下半年  
   73%
(75) is the process of determining, documenting, and managing stakeholder needs and requirements to meet project objectives.
 

ping
ping通过发送"Internet控制报文协议(ICMP)"回送请求/应答报文来验证与另一台TCP/IP计算机的IP级连接。回送请求/应答报文的接收情况将和往返过程的次数一起显示出来。ping是用于检测网络连接性、可到达性和名称解析的疑难问题的主要TCP/IP命令。如果不带参数,ping将显示帮助。
1)语法格式
2)参数说明
参数如下表所示。
ping的选项
未完......点击标题查看......

 题号导航      2008年下半年 信息系统项目管理师 上午试卷 综合知识   本试卷我的完整做题情况 
1 /
2 /
3 /
4 /
5 /
6 /
7 /
8 /
9 /
10 /
11 /
12 /
13 /
14 /
15 /
 
16 /
17 /
18 /
19 /
20 /
21 /
22 /
23 /
24 /
25 /
26 /
27 /
28 /
29 /
30 /
 
31 /
32 /
33 /
34 /
35 /
36 /
37 /
38 /
39 /
40 /
41 /
42 /
43 /
44 /
45 /
 
46 /
47 /
48 /
49 /
50 /
51 /
52 /
53 /
54 /
55 /
56 /
57 /
58 /
59 /
60 /
 
61 /
62 /
63 /
64 /
65 /
66 /
67 /
68 /
69 /
70 /
71 /
72 /
73 /
74 /
75 /
 
↓第75题