第74题      2017年上半年 系统集成项目管理工程师 上午试卷 综合知识
所属知识点   专业英语             

 
( )is a project management technique for measuring project performance progress.It has the ability to combine measurements of the project management triangle: scope,time and costs.
 
 
  A.  Critica1 path method(CPM)
 
  B.  Earned value management(CEV)
 
  C.  Net present value method(NPVM)
 
  D.  Expert judgment method(EJM)
 
 
 


↓第74题
  专业英语 知识点 更多相关真题:    更多>>  
 
  第71题    2013年上半年  
Modem computers based on (71) are millions to billions of times more capable than the early computers, which occupy a fraction of the space. Simple computers are small enough to fi..
  第75题    2017年下半年  
( )is the approved version of the time-phased project budget excluding any management reserves which can only be changed through formal change control precedures and is used as a..
  第73题    2011年下半年  
The project schedule is more than a document that lays out the activities over time to represent the time dimension of the project, it is a management tool to be used for decision ..
 
题号导航      2017年上半年 系统集成项目管理工程师 上午试卷 综合知识   本试卷我的完整做题情况
第1题 /
第2题 /
第3题 /
第4题 /
第5题 /
第6题 /
第7题 /
第8题 /
第9题 /
第10题 /
第11题 /
第12题 /
第13题 /
第14题 /
第15题 /
 
第16题 /
第17题 /
第18题 /
第19题 /
第20题 /
第21题 /
第22题 /
第23题 /
第24题 /
第25题 /
第26题 /
第27题 /
第28题 /
第29题 /
第30题 /
 
第31题 /
第32题 /
第33题 /
第34题 /
第35题 /
第36题 /
第37题 /
第38题 /
第39题 /
第40题 /
第41题 /
第42题 /
第43题 /
第44题 /
第45题 /
 
第46题 /
第47题 /
第48题 /
第49题 /
第50题 /
第51题 /
第52题 /
第53题 /
第54题 /
第55题 /
第56题 /
第57题 /
第58题 /
第59题 /
第60题 /
 
第61题 /
第62题 /
第63题 /
第64题 /
第65题 /
第66题 /
第67题 /
第68题 /
第69题 /
第70题 /
第71题 /
第72题 /
第73题 /
第74题 /
第75题 /