免费智能真题库 > 历年试卷 > 系统集成项目管理工程师 > 2011年下半年 系统集成项目管理工程师 上午试卷 综合知识
  第72题      
  章/节:   专业英语       

 
A project manager is called to an informal meeting with the customer and a problem is raised. This problem has major implications for the project manager’s company, but the customer wants to pursue a solution at the meeting. The project manager should (72).
 
 
  A.  Tell the customer that he will not address any problems
 
  B.  Tell the customer that the problem is not sufficiently defined to company to a solution
 
  C.  Collect as much information on the problem without committing his company to a solution
 
  D.  Give the customer a range of solutions that might be acceptable to his company
 
 
 

 
  第72题    2019年下半年  
   76%
( )seeks to perform root cause investigation as to what is Ieading identified trends.
  第74题    2014年上半年  
   59%
In project management , a (73 ) is a listing of a project’s milestones, activities, and deliverables, usually with..
  第75题    2021年上半年  
   91%
( ): information is not disclosed to unauthorized indivi duals.
   题号导航      2011年下半年 系统集成项目管理工程师 上午试卷 综合知识   本试卷我的完整做题情况  
1 /
2 /
3 /
4 /
5 /
6 /
7 /
8 /
9 /
10 /
11 /
12 /
13 /
14 /
15 /
 
16 /
17 /
18 /
19 /
20 /
21 /
22 /
23 /
24 /
25 /
26 /
27 /
28 /
29 /
30 /
 
31 /
32 /
33 /
34 /
35 /
36 /
37 /
38 /
39 /
40 /
41 /
42 /
43 /
44 /
45 /
 
46 /
47 /
48 /
49 /
50 /
51 /
52 /
53 /
54 /
55 /
56 /
57 /
58 /
59 /
60 /
 
61 /
62 /
63 /
64 /
65 /
66 /
67 /
68 /
69 /
70 /
71 /
72 /
73 /
74 /
75 /
 
第72题    在手机中做本题