Project selection methods involve measuring value or attractiveness to the project owner or sponsor and may include other organizational decision criteria.(74)is not a project selection method.
 
  A.  Scoring models
 
  B.  Flow charting
 
  C.  Expert judgment
 
  D.  Benefit contribution




 
 
相关试题     专业英语 

  第74题    2014年上半年  
Requirements management is the process of (73),analyzing,tracing,prioritizing and agreeing on requirements and then controlling changes and communi..

  第73题    2016年上半年  
The scope management plan is how the team will prepare the(73)a document that includes descriptions of create the WBS, verify completion of the proj..

  第75题    2022年上半年  
Advancements in ()have contributed to the growth of the automotive industry through the creation and evolution of self-driving vehicles.