2025年上半年 上午试卷 综合知识
第 75 题
知识点 DM  
章/节 专业英语  
 
 
Precedence Diagramming Method(PDM) is a method used in activity sequencing.There are four types of dependencies or precedence relationships in PDM. The initiation of the successor activity depends upon the completion of the predecessor activity is called(75).
 
  A.  Finish-to-Finish
 
  B.  Finish-to-Start
 
  C.  Start-to-Finish
 
  D.  Start-to-Start




 
 
相关试题     专业英语 

  第72题    2020年下半年  
()can be scripted as a new science and technology,which is used to simulate human intelligence namely, computers simulate the way of human’s think..

  第73题    2019年上半年  
( ) are those costs that cannot be directly traced to a specific project and therefore will be accumulated and allocalted equitably over multiple proj..

  第72题    2009年下半年  
The strategies for handling risk comprise of two main types:negative risks, and positive risks. The goal of the plan is to minimize threats and maxi..

 
知识点讲解
· DM
 
        DM
        DM(Delta Modulation)即增量调制,又称ΔM调制,是最简单的有损预测编码方法,早期在数字电话中被采用,是一种最简单的差值脉冲编码。实际的采样信号与预测的采样信号的差的极性若为正,则用1表示,反之则用0表示。由于DM编码只用1位对声音信号进行编码,所以DM系统又称1位系统。



更多复习资料
请登录电脑版软考在线 www.rkpass.cn

京B2-20210865 | 京ICP备2020040059号-5
京公网安备 11010502032051号 | 营业执照
 Copyright ©2000-2026 All Rights Reserved
软考在线版权所有