第 75 题
章/节 专业英语  
 
 
Setting redundant componernts in subsystem to handle with the risks brought by the defaults of original components,what kind of risk response strategy is this?(75)
 
  A.  risk avoidance
 
  B.  risk acceptance
 
  C.  risk mitigation
 
  D.  contingency plan




 
 