A(74)is a type of bar chart that illustrates a project schedule. It illustrates the start and finish dates of the terminal elements and summary elements of a project.
 
  A.  gantt chart
 
  B.  project histogram
 
  C.  milestone chart
 
  D.  project flowchart




 
 