全部科目 > 信息系统项目管理师 >
2013年下半年 上午试卷 综合知识
第 74 题
章/节 专业英语  
 
 
A(74)is a type of bar chart that illustrates a project schedule. It illustrates the start and finish dates of the terminal elements and summary elements of a project.
 
  A.  gantt chart
 
  B.  project histogram
 
  C.  milestone chart
 
  D.  project flowchart




 
 
相关试题     专业英语 

  第71题    2020年下半年  
The patterns of()show the next probable behavior of a person or market without a logical explanation as to why.

  第71题    2013年下半年  
Each machine in the internet is assigned a unique network address,called(71),that is used to identify the machine for communication purposes.

  第75题    2015年下半年  
If the approved change requests have an effect on the project scope, then the corresponding component documents and cost baselines, and(75 )of the p..




更多复习资料