In the (74)phase team members begin to work together and adjust their work habits and behaviors to support the team. The team learns to trust each other.
 
  A.  storming
 
  B.  performing
 
  C.  norming
 
  D.  adjourning




 
 
相关试题     专业英语 

  第71题    2011年下半年  
Quality planning tools are often used to help plan effective quality management activities.(71) is one of such tools,which involves company actual or ..

  第72题    2015年上半年  
When multiple routers are used in interconnected networks,the routers exchange information about()using a dynamic routing protocol.

  第75题    2008年下半年  
Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones...