In the (74)phase team members begin to work together and adjust their work habits and behaviors to support the team. The team learns to trust each other.
 
  A.  storming
 
  B.  performing
 
  C.  norming
 
  D.  adjourning




 
 
相关试题     专业英语 

  第72题    2010年上半年  
(72)describes, in detail, the project’s deliverables and the work required to create those deliverables.

  第73题    2008年下半年  
The Estimate Activity Resource process is closely coordinated with the (73)process.

  第72题    2011年下半年  
A (72) is a collection of projects and other work that are grouped together to facilitate effect -ive management of that work to meet strategic busine..