第 75 题
章/节 专业英语  
 
 
The (75) is primarily concerned with acceptance of the deliverables.while quality control is primarily concerned with correctness of the deliverables and meeting the quality requirements specified for the deliverables.
 
  A.  verify scope
 
  B.  define scope
 
  C.  quality assurance
 
  D.  validate scope




 
 