全部科目 > 信息系统项目管理师 >
2015年上半年 上午试卷 综合知识
第 73 题
章/节 专业英语  
 
 
Before a project schedule can be created,the schedule maker should have a(),an effort estimate for each task,and a resource list with availability for each resource.
 
  A.  work breakdown structure
 
  B.  baseline
 
  C.  software requirements specification
 
  D.  plan




 
 
相关试题     专业英语 

  第72题    2016年上半年  
(72):a method of obtaining early feedback on requirements by providing a working model of the expected product before actually building it.

  第71题    2009年下半年  
The (71) process ascertains which risks have the potential of affecting the project and documenting the risks' characteristics.

  第73题    2010年上半年  
Fair and(73)competition in government procurement around the world is good business and good public policy. Competitive pricing, product (74)and p..