2015年上半年 上午试卷 综合知识
第 73 题
章/节 专业英语  
 
 
Before a project schedule can be created,the schedule maker should have a(),an effort estimate for each task,and a resource list with availability for each resource.
 
  A.  work breakdown structure
 
  B.  baseline
 
  C.  software requirements specification
 
  D.  plan




 
 